    • Conform to general health, safety and welfare (CC001)
    • Conform to productive working practices (CC002)
    • Move, handle and store resources (CC003)
  • Steel Frame Systems Core Trade Competencies (SFS001)
    • Steel Frame Systems Core Trade Competencies (SFS001)
  • Trade specific competencies
    • Installing Steel Framed Systems (SFS002)
    • Install Sheathing Boarding (SFS003)
    • Application of Breather Membranes (SFS004)
    • Installation of External Insulation (SFS005)
  • Experience
  • Behaviours
  • References/Glossary
Steel Framed Systems

Installing Steel Framed Systems (SFS002)

You must be able to:

  • Comply with project drawings, specifications, and manufacturers specifications to set out head and base tracks by using gridlines and datums, ensuring that they have sufficient bearing throughout/across levels

  • Install Z bars as necessary as shown on project specific drawings and manufacturers’ 'specifications

  • Install hot roll post in accordance with the manufacturers’ specifications using correct fixings

  • Comply with specified drawings to:

    • install studs in their designated positions

  • Form openings by:

    • creating lintels

    • jambs

    • cills

    • install cleats

  • Identify and install compound details

  • Ensure deflection detail is installed correctly and takes into account manufactures’ specifications

  • Install various types of fixings for their specific purposes, contributing to the overall integrity and safety of installations, ensure that all fixings are correctly installed according to the provided drawings and manufacturers’ specifications

Next: Knowledge

You must know and understand:

  • How to interpret and set out work area according to project drawings, specifications, and manufacturers' specifications in relation to:

    • gridlines and datums

    • z bars

    • head and base tracks

    • studs

    • cleats

    • torsional restraints

  • How and why a Hot works permit would be required from the Principal Contractor. PPE specific to employers Risk Assessment to be enforced

  • How to install hot roll post in accordance with the manufacturers specifications using correct fixings

  • How to interpret and set out work area according to project drawings, specifications, and manufacturers' specifications in relation to:

    • studs

    • lintels

    • jambs

    • cills

    • deflection detail

    • laser

    • track

  • How to form compound details and install insulation to prevent cold bridging

  • Why the use and sequencing of cleats within a specific project is important

  • The importance of the type of fixing that should be used for their specific purposes, contributing to the overall integrity and safety of installations, ensuring that all fixings are correctly installed according to the provided drawings and manufacturers' specifications

  • Why it is important to identify and follow the installation quality requirements

  • How and why operative care and maintenance of all hand and power tools and associated equipment is carried out

  • The relevance of an assessment of significance

  • How to recognise specific requirements for structures of special interest, traditional construction, hard to treat buildings and historical significance

  • That a construction product choice, substitution or recommendation cannot be made

  • That if information on construction products is communicated information must be passed on accurately and without changes from that created by the relevant authority

  • The implications of incorrect installation

  • The characteristics, quality, uses, limitations and defects associated with the following resources for the installation of the SFS

    • access equipment in accordance with site rules

    • cutting equipment

    • hand and power tools (battery and 110)

    • drilling equipment and mechanical fasteners

    • fixings

    • light gauge steel frame components

  • Why the maintenance of tools and equipment is important

  • The organisational procedures for reporting issues or defects with tools and resources

  • How methods of work to meet the specification are carried out, and any problems reported

  • The hazards associated with the resources and methods of work, and how they are overcome

  • How risk of damage to the work and the surrounding area is minimised, and the importance of doing so

Next: Install Sheathing Boarding (SFS003)